We own our equipment.

“We make it happen.”

1. Pool Purchase

  • Sign contract
  • Rescission period (3 day)
  • Up front deposit

2. We draw plans, get engineering and turn in for permits (usually takes 1-15 days).

3. We pull permits (time varies depending on building department).

4. We start construction (dig starts usually within 15 days of obtaining permits, pool completion within 60-90 working days of dig).

Payment Schedule

DIG15% of contract due
ROUGH PLUMBING, ROUGH ELECTRICAL, REBAR35% of contract due
INSPECTIONS, GUNITE30% of contract due
TILE, COPING, DECKING15% of contract due
PLASTER5% of contract due