1. Pool Purchase

  • Sign contract
  • Rescission period (3 day)
  • Up front deposit $0

2. We Turn In For Permits.

3. We Pull Permits (usually takes 1-10 days).

4. We Start Construction.

Week 1...

DIG............................................15% of contract due

Week 2...

PLUMBING
ELECTRICAL
REBAR.......................................35% of contract due

Week 3...

INSPECTIONS
GUNITE.....................................30% of contract due

Week 4 & 5...

TILE
DECKING..................................15% of contract due

Week 6...

EQUIPTMENT SET

CLEAN UP

Week 7...

PLASTER.....................................5% of contract due